pre-pour inspection failed
we're told was due to village requirements for the cold.
GC is positive that is corrected and will pass today...

If passes, maybe the concrete will be poured today....
This would require thermal blankets to be draped over the foundation walls for 3 days, which would mean no more work this week. Still is progress...
They'd strip foundation wall/ backfill/ schedule backfill inspection all next week maybe..
Maybe start framing the week of the 8th?