Sunday, January 31, 2010

Sat,... work continues...

Here's some more pics of the foundation.
Waterproofing has been applied and drainage pipes put in place

Tuesday, January 26, 2010

Tuesday, Jan 26th update #2

inspection passed, concrete walls poured today!
YAHOO! LOVE TO SEE THE CONTINUED PROGRESS!

:)

Tuesday, Jan 26th update

pre-pour inspection failed
we're told was due to village requirements for the cold.
GC is positive that is corrected and will pass today...

If passes, maybe the concrete will be poured today....
This would require thermal blankets to be draped over the foundation walls for 3 days, which would mean no more work this week. Still is progress...
They'd strip foundation wall/ backfill/ schedule backfill inspection all next week maybe..
Maybe start framing the week of the 8th?
We'll see...

Monday, January 25, 2010

Mon, Jan 25th

Crews showed up at 9:15 or so...
finishing framing forms for foundation walls
Pre-pour inspection is scheduled this afternoon with pouring scheduled tomorrow

Thursday, January 21, 2010

Thurs, Jan 21st - work continues,..


It looks as if crew is stripping the footings today and starting to frame the foundation walls....
There's a flatbed of lumber, some black hose( not surewhat that's used for...)




Oh, the foundation wall forms!


The black tubing is circled around the cement footings,...maybe it's filled with some kind of hot water or something to keep it warm.... 

Friday, Jan 22nds,...
Glad that work is continuing despite the cold....
maybe mother nature will cooperate and the weather won't be as bad as forecasted next week, too....

Wednesday, January 20, 2010

Wed, Jan 20th - Footings Poured

Watching the cement truck and crew pour/ spread the cement was alot of fun.





Crews finished pouring before 10:00am - awesome!
I think the hay is placed over the concrete to help it cure.
We're expecting freezing rain today/tonight, so hope all goes well.






<--Garage will be here...

Tuesday, January 19, 2010

Prep Footings/ Footing inspection = PASSED (Tues, 1/19)

Work completed on time and we passed our first village inspection....

Monday, January 18, 2010

Mon. , Jan 18th!


Tree Protection fence and site fence was put up today.


FR demo completed today. Garage needs to be completed tomorrow morning so concrete sub can frame the footing posts for inspection tomorrow afternoon.... Think it can happen- Hope it happens!

Thurs, Jan 14th - Mon 18th Excavation

Backhoes and crew reported for duty on Thurs. Jan 14th.
After Thursday's work and 1/2 day's work fri. there is sizeable hole in backyard.


The joys of construction/ demolition, our internet cable was accidentally cut by the backhoe crane, so we were without internet until the fine folks at comcast arrived friday afternoon to run a new line....
A small inconvenience,...

Today, (monday 18th) the garage slab will be demolished and a hole dug if all goes to plan

Tomorrow, the pre-footing inspection is planned.

The work kept a sick Andy and well Thomas entertained,....

Wednesday, January 13, 2010

Backhoes reporting for Duty

 Backhoes are here,....no permit yet,... but maybe tomorrow,..


MAMA  & BABY

GOOD NEWS!

Chris from Reveal is picking up permit this morning.Yeah, it's finally issued!
Plan is to demolish garage slab/ patio slab and excavate this afternoon and next 2 .5 days.
If all goes well, they will prep for pre-footing inspection and schedule monday and pour footings tuesday. Hope everything goes to plan!

Monday, January 11, 2010

Week of Jan 11th -update

Permit issuance is still dependant on trades submitting their registration to Village. The Village has only received from Electrician, it seems....
That's disappointing...
But, Chris of Reveal seemed to say that it will be done soon and excavation would start this week. The Excavation guy is supposed to be coming out today to see how bad the frost is and plan for work this week...That's encouraging news...

Week of Jan 11th...

It's monday, we've picked out our selections for ext. doors, windows, etc. as scheduled...
Weather is a little better than last week, so we're hopeful that demo of electrical and excavation will be completed this week and possibly footing prep, footing pour, etc...
As of right now crews are about 1 week off of the latest schedule due to cold weather/village permit issuance delay...

Wednesday, January 6, 2010

Garage demolished

Temp 19 degrees or so today.
Crew began at 7:45am and ended at about 3:30pm. Joe and Chris of Reveal dropped by to check on the subs doing the work. Subs were very polite and professional. Here are some pics of the demo.

See the lovely tar that is revealed on our house? I guess a former owner or builder used on brick to attach former garage to our house.....LOVELY!

All went well with the demo with only one basement storm window getting broken accidentally.
That window will be enclosed in the new garage anyway... For now, I'm putting our trash cans in front of it to hide until can be cleaned up. Will mention to Joe when we meet with him tonight.....


 From upstairs window,..part of roof is gone....


Now, the roof is gone....








garage is GONE!









Side view (see broken storm window)









yuck-TAR city....hope builder or mason can remove it on the brick that will be exposed
I'm sure they can, or maybe easier to replace it....

Tuesday, January 5, 2010

Dumpster dropped, ok from village to go forward with demo


 Wednesday, Jan 6th crew begins work to demolish the garage.